Aquifer Storage and Recovery for sustainable banana production in the Magdalena region, Colombia – RECAR-BA

Improving water management techniques in the banana sector is one of the prioritized topics for the coming years and is a cornerstone of the bilateral agenda on circular agriculture of the Dutch Embassy in Colombia. As part of the Partners for Water program, a project has been initiated to foster collaboration between Dutch and Colombian stakeholders in the field of aquifer storage and recovery for sustainable banana production in Colombia. The project is executed by a Dutch-Colombian consortium composed by Deltares, IHE Delft Institute, Wageningen Environmental Research, and Fundación Herencia Ambiental Caribe in collaboration with ASBAMA, BANASAN, TECBACO, and ASORIOFRIO, among other key stakeholders.

Background

The Netherlands is internationally recognised for its expertise in water management, which is one of the pillars of the country's various bilateral relations. Through the Netherlands International Water Ambition (IWA), it seeks to promote water security and to optimise the Dutch contribution to this end. This is done through strategic partnerships with seven delta countries, including Colombia.

The agricultural sector in Colombia is one of the most important in the country and, at the same time, one of the most affected by climate change. In the banana sector, Colombia is the fourth largest supplier of bananas in the world, with the Netherlands being one of the main export destinations. Banana production (often accompanied by plantain cropping) in the department of Magdalena is threatened by several hazards, including a shortage of fresh water for irrigation, salinisation of water and soils, and the lack of appropriate irrigation systems. In addition, banana production areas are located between two systems of great natural and cultural importance and capital (the Ciénaga Grande de Santa Marta and the Sierra Nevada de Santa Marta), so proper water management to produce these crops is essential to maintain and protect the surrounding ecosystems.

In December 2020, the Government of the Netherlands, through the Partners for Water programme, assigned the present project to Deltares, the applied institute for water and subsurface, and partners IHE Delft Institute for Water Education, Wageningen Environmental Research and Fundación Herencia Ambiental Caribe, in order to contribute to the sustainability of production chains in the agricultural sector, specifically in relation to banana production.

Ambition

This project seeked to explore alternative water management techniques to improve the management of water resources in the Rio Frio and Rio Sevilla basins in the department of Magdalena, thereby promoting sustainable banana production in the area. The focus to achieve this objective was on aquifer storage and recovery techniques (also called artificial recharge techniques or ASR - Artificial Storage and Recovery). The project targets medium-sized banana producers (between 10 and 50 hectares). This project aimed at providing results that 1) inform the feasibility of artificial recharge techniques in the area, and 2) provide the first steps for producers to adapt storage and recovery techniques, in case they are considered feasible. This is expected to help to move water management for banana crops towards a sustainable scheme that contributes to fair and equitable access to water for different water users.

Project activities and approach

The activities were carried out in four phases. In each phase, both technical and local consultation activities (through workshops) took place, seeking the continuous participation of the project's key counterparts, namely the banana-producers association - ASBAMA and the trading companies BANASAN and TECBACO, as well as the users association Asoriofrio among other stakeholders. This exchange helped the project to be better focused on the counterparts and stakeholders needs.

Beeld: ©LAN Bogota

During the first phase, carried out from January to March 2021, a dialogue was established with multiple stakeholders to define their interest and participation in the project. Additionally, technical information was collected and the banana producing areas with the greatest need and potential for ASR systems, as well as the potential beneficiaries of the project were identified.

Phase 2 was focused on understanding the current conditions of the basin, in relation to hydrological and hydrogeological aspects and their relationship with current and future water supply and demand. With this information, threats and risks to the banana sector were identified.

Phase 3 included the evaluation of the potential for artificial recharge in the aquifers of the river basins, through the identification of the most appropriate techniques to use, the potential zones for their adaptation and finally the selection of the potential sites to be studied in more depth.

Finally, phase 4 consisted of an indicative cost-benefit analysis to explore alternatives for improving water management techniques for banana production, a feasibility study including and addressing limiting factors, a work plan for the implementation of a pilot project for artificial recharge of aquifers, and the conceptual demonstration of a decision support system to support decisions on the feasibility of installing an artificial recharge system.

The activities of these four phases resulted in a set of calculations, maps, guidelines and tools to be used when the installation of ASR pilots for medium-sized banana producers is considered in the Río Frío and Río Sevilla basins, as explained in the following video: https://www.youtube.com/watch?v=8M8jlUbUpTQ

The water balance results show that in the wet season, there is enough water in the basins for infiltration and that this would not affect ecological flows. The cost-benefit analysis showed a positive benefit of implementing ASR infiltration wells in the studied plots, and a positive return of investment. The recommendations for follow up include a water quality study and the installation of an ASR pilot in one of the plots, to locally demonstrate the benefits of these systems. The introduction and upscaling of ASR techniques will contribute to anticipating possible changes of international certification standards including new requirements on good water practices for bananas production, maintaining export markets and, therefore, guaranteeing in turn a more stable and fair income.

Beeld: © Marta Faneca Sánchez

If you want to download this project summary follow the links below, also available in Spanish. Interested in receiving more information? Please contact us:

LAN Bogota
BOG-LNV@minbuza.nl

Deltares
Marta Faneca Sánchez
Marta.Faneca@deltares.nl